IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO.7627 OF 2021 IN FAST/10483/2021 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT, OMERGA

VERSUS

NAGNATH GOVIND REDDY AND OTHERS ...

Advocate for Applicant : Mr. D.S. Mutalik, Advocate h/f Mr. U.S. Malte AGP for Respondents - State : Mr. S.B. Yawalkar ...

CORAM : SANJAY A. DESHMUKH, J.

DATE : 26th OCTOBER, 2023 PER COURT :

1.

Though duly served, none appears for respondent No.1. 2.

Heard learned advocate for applicant and learned AGP for respondents - State.

3.

This application is filed for condonation of delay of 693 days caused in filing the appeal.

4.

Considering the grounds mentioned in the application and facts and circumstances of present case, in the interest of justice, the application is allowed in terms of prayer clause 'B'. Appeal be registered. Application is accordingly disposed off. (SANJAY A. DESHMUKH, J.) SVH