The Ex. Engineer, Irrigation Project Strengthening Div. Omerga v. Ramesh Mahadu Mule And ORS
36(b)-ca-7176-2021.odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 7176 OF 2021 IN FIRST APPEAL STAMP NO. 10524 OF 2021 The Executive Engineer, Irrigation Project Strengthening Division, Omerga ... Applicant
Versus
Ramesh Mhadu Mule and others ... Respondents ....
Mr. P. B. Patil, Advocate for applicant Mr. S. N. Morampalle, AGP for respondent Nos. 2 and 3 ....
CORAM : R. G. AVACHAT, J.
DATED : 25th OCTOBER, 2021 PER COURT :- .
Heard.
2.
For the reasons given in the application, the same is allowed in terms of prayer clause (B).
3.
Appeal be registered.
4.
On registration of appeal, issue notice to the respondents, returnable after twelve (12) weeks. 5.
Learned AGP waives service for respondent Nos. 2 and 3. [ R. G. AVACHAT, J. ] SMS