Hdfc Ergo General Insurance Co. Ltd. v. Chandrabhan Vithalrao Navghare And ANR
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 915 CIVIL APPLICATION NO.4450/2016 IN FAST/10261/2016 WITH WITH CA/4451/2016 IN FAST/10261/2016 with CA 11201/2016 CHANDRABHAN VITHALRAO NAVGHARE
VERSUS
HDFC ERGO GENERAL INSURANCE CO. LTD. AND ANR ...
Advocate for Applicants : Mr. S.G. Chapalgaonkar Mr.Kalani Pravin N.Adv. For R/1 ...
CORAM : P.R. BORA, J.
Dated: August 12, 2016 ...
PER COURT :- 1) Heard the learned Counsel for applicant and learned counsel for original claimant. Delay of 74 days has occurred in filing the present appeal by the Insurance Company.
2) Learned Counsel appearing for the original claimant has opposed for condoning the delay, stating that the reasons assigned are insufficient. 3) For the reasons stated in the application, which according to me are just and sufficient, the delay caused in filing the appeal stand condoned. 4) The appeal be registered in accordance with BDV
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD law. Application for condonation of delay is disposed of.
5) On registration of the appeal, issue notice to respondents, returnable after six weeks. Learned Counsel waives service for original claimant. 6) Place the appeal for admission after six weeks. Application for withdrawal of the amount shall be considered at the time of admission of the appeal.
( P.R. BORA, J. ) ...
BDV