The Executive Engineer, Lower Dudhana Project, Selu Thr Jalna Irrigation Division, Jalna v. Ramesh Manoharrao Kulkarni And ORS
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CA/6248/2016 IN FAST/10345/2016 THE EXECUTIVE ENGINEER, LOER DUDHANA PROJECT,SELU NOW EXE. ENGINEER JALNA IRRIGATION.
VERSUS
RAMESH MANOHARRAO KULKARNI ...
Advocate for Applicant : Mr. Ruturaj C.Patil, Mr. KN Lokhande, AGP for Resp.Nos. 2 & 3;
...
CORAM : P.R. BORA, J.
Dated: July 29, 2016 ...
PER COURT :- 1) Learned AGP appears for Respondent Nos.2 &
3. Service is complete. Heard learned counsel for respective parties.
2) For the reasons stated in the application, which according to me are just and sufficient, delay of 396 days occurred in filing the present appeal is condoned. Appeal be registered in accordance with law. CA for condonation of delay disposed of. 3) Issue notice on appeal to respondents, returnable after six weeks. Learned AGP and learned Counsel waive service for respective respondents. 4) Place the appeal for admission after six weeks.
( P.R. BORA, J. ) ...
BDV