IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD (1) CA NO.5354/2016gr 914 CIVIL APPLICATION NO. 5354 OF 2016 IN FAST/29530/2015 WITH CA/5356/2016 IN FAST/29251/2015 WITH CA/5358/2016 IN FAST/29241/2015 WITH CA/5360/2016 IN FAST/29258/2015 WITH CA/5362/2016 IN FAST/29248/2015 WITH CA/5363/2016 IN FAST/29245/2015 BHAGABAI PREMRAO MHASKE

VERSUS

THE EXECUTIVE ENGINEER, NIMNA DUDHANA PROJECT DIVISION, SAILU AND ANR ...

Advocate for Applicant : Mr.Gore Ravindra Vitthal AGP for Respondent State: Mr.C.V.Dharurkar Mr.R.C.Patil, Adv., for respondent no.1.

...

CORAM : P.R. BORA, J.

Dated: May 03, 2016 ...

PER COURT :- 1.

Heard learned Counsel appearing for the applicants and the learned Counsel appearing for the respondent acquiring body.

2.

Having considered the contentions raised in the present applications and having regard to the defenses raised by the acquiring body, I deem it appropriate to allow the original claimants to AGP/-

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD (2) CA NO.5354/2016gr withdraw 50% of the amount deposited in this Court on submitting an undertaking that if any adverse order is passed, and the amount of compensation is reduced, they will re-deposit the amount, as may be specified, in the period prescribed by the Court.

Balance 50% amount be invested in a fixed deposit in any nationalized Bank for the period till disposal of the appeal.

Civil Applications for withdrawal of amount stand disposed of.

( P.R. BORA, J. ) ...

AGP/-