IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 1068 CIVIL APPLICATION NO.6001 OF 2019 IN FAST/10838/2019 WITH CA/6003/2019 IN FAST/10834/2019 WITH CA/6005/2019 IN FAST/10831/2019 THE EXE ENGINEER, LATUR MEIUM PROJECT DIV., LATUR THR EXE ENGINEER, LOWER TERNA

VERSUS

VINAYAK NIVRUTI JATAL ...

Advocate for Applicant : Mr. Patil Ruturaj C. Advocate for Respondent : Mr. S.S. Panale ...

CORAM : SMT. VIBHA KANKANWADI, J.

DATE : 26th JULY 2019 ORDER :

.

Present applications have been filed for getting the delay of 556 days condoned in filing first appeals. The applicant No.1-is the acquiring body who intends to challenge the judgment and award passed by the Reference Court. The learned Advocate appearing for the respondent has no serious objection for condoning the delay. Under such circumstance, for the reasons stated in the application, the delay stands condoned.

2.

Civil Applications stand allowed and disposed of accordingly.

3.

Registry to verify and register the first appeals and place it for further consideration on 16.01.2020.

( Smt. Vibha Kankanwadi, J. ) Shubham/