Executive Engineer, Irrigation Project Majbutikaran Division, Omerga Thr M.K.V.D.C. Pune And ORS v. Nagabai Babu Wale
IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD 9 CIVIL APPLICATION NO.6699 OF 2018 IN FAST/10764/2018 WITH CA/6703/2018 IN FAST/11064/2018 WITH CA/6705/2018 IN FAST/11069/2018 WITH CA/6701/2018 IN FAST/11074/2018 EXECUTIVE ENGINEER, IRRIGATION PROJECT MAJBUTIKARAN DIVISION, OMERGA THR M.K.V.D.C. PUNE AND OTHERS
VERSUS
MADHUBAI VITHAL INGALE ...
Advocate for Applicants : Mr. Patil Umakant K. and Mr. Bhalerao Sudhir Govind Advocate for Respondents : Ms. Sunita D. Shelke h/f. Mr.Patil Laxmikant C.
...
CORAM : SANDIPKUMAR C. MORE, J.
DATE : 23.01.2023 PER COURT :
Heard rival submissions. The Acquiring Body in all these applications is seeking condonation of delay of 1010 days which appears to be caused due to obtaining sanctions at various stages. The learned counsel for the respondents -claimants submits that the Acquiring Body is negligent since beginning. However, considering the statutory right of the applicants, the delay of 1010 days stands condoned in all these applications.
2.
Appeals be placed for admission after removal of office objections, if any.
3. Applications are disposed of accordingly. (SANDIPKUMAR C. MORE) JUDGE ...
shp/-