The Branch Manager The New India Assurance Company Ltd v. Babasaheb Pandharinath Vidhate Thorugh Samadhan Pandharinath Vidhate And Others
2025:BHC-AUG:10867 (1) 118-ca-4015-2024.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 4015 OF 2024 IN FAST/10252/2024 THE BRANCH MANAGER THE NEW INDIA ASSURANCE COMPANY LTD
VERSUS
BABASAHEB PANDHARINATH VIDHATE THORUGH SAMADHAN PANDHARINATH VIDHATE AND OTHERS ...
Mr. M. M. Ambhore, Advocate for Applicant.
Mr. Rahul R. Karpe, Advocate for Respondent No.1. Mr. A. B. Chormal, Advocate for Respondent Nos.2 and 3. ...
CORAM : S. G. CHAPALGAONKAR, J.
DATED : 15th APRIL, 2025.
P.C.:- 1.
Heard learned Advocate appearing for respective parties. 2.
By this application, applicant seeks to condone delay of 9 days caused in filing Appeal.
3.
Having considered reasons as stated in application, delay is sufficiently explained. Hence, following order:
ORDER
a.
Civil Application is allowed.
b.
Delay of 9 days caused in filing appeal is hereby condoned. c.
Appeal be registered.
(S. G. CHAPALGAONKAR) JUDGE Devendra/April-2025