Shyam Rameshwar Darak v. Vaijanath Vishwanath Ture And ORS
9179.17CA.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 949 CIVIL APPLICATION NO.9179 OF 2017 IN FIRST APPEAL [STAMP] NO.11852 OF 2017 SHYAM RAMESHWAR DARAK
VERSUS
VAIJANATH VISHWANATH TURE & OTHERS ...
Mr.S.S.Rathi, Advocate for the applicant.
Mr.Jeevan R. Patil, Advocate holding for Mr.A.G.Kanade, Advocate for respondent no.7.
...
CORAM : V. K. JADHAV, J.
DATED : 01.09.2021 PER COURT :
1] Heard learned counsel for the applicant and learned counsel for respondent no.7 - insurer. The applicant is the Contractor and the party respondent in the proceedings before the Commissioner for Employee's Compensation. 2] So far as penalty part is concerned, appeal is preferred by the applicant - Contractor to that extent only, which is delayed by 38 days.
3] Thus, considering the delay of 38 days which is satisfactorily explained, I am inclined to condone the delay. Hence, the following order is passed :
9179.17CA.odt
ORDER
Civil Application is allowed in terms of prayer clause-B. Accordingly, Civil application is disposed of. [V. K. JADHAV, J.] DDC