The Ex. Engineer, Minor Irrigation Department Osmanabad v. Sattar Yasin Attar And ORS
{1} 48 sr.no..odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO.4246 OF 2020 IN FA/946/2020 WITH CA/4242/2020 IN FA/947/2020 THE EX. ENGINEER, MINOR IRRIGATION DEPARTMENT OSMANABAD
VERSUS
SATTAR YASIN ATTAR AND ORS ...
Advocate for Applicant : Mr. Sunil D. Kaldate AGP for Respondent No.2 and 3 - State : Mr. B. V. Virdhe Advocate for Respondent-claimant/s : Mr. P. B. Rakhune ...
CORAM : V.K. JADHAV, J.
DATE : 6TH NOVEMBER, 2020.
PER COURT:
Heard learned counsel for the applicant - Acquiring Body. It appears that conditional stay was granted. However, the amount of compensation could not be deposited within the stipulated time. 2.
The learned counsel for the applicant - Acquiring Body seeks extension of time. He submits that the cheque of the compensation amount has been received and the same would be deposited within a period of two weeks.
3.
The other side has no objection for depositing the amount of compensation through cheque.
{2} 48 sr.no..odt 4.
In view of the same, the time to deposit the compensation amount is extended for a period of two weeks. 5.
Office to accept the cheque if it is deposited within a period of two weeks.
6.
Interim order of stay granted earlier to continue subject to deposit of compensation amount within extended period. 7.
Civil applications are accordingly disposed of. [ V. K. JADHAV ] JUDGE grt/-