Khilari Infrastructure Pvt Ltd Jv Through Authorized Person Sajit Husain Inayat Husain v. The State Of Maharashtra And Others
1 923-wp 5116-2019.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD WRIT PETITION NO. 5116 OF 2019 Khilari Infrastructure Pvt. Ltd., (J.V.) Through its Authorized Person Sajid Husain Inayat Husain .. Petitioner
Versus
The State of Maharashtra and others .. Respondents Mr. R. N. Dhorde, Senior Advocate i/by Mr. Vikram R. Dhorde, Advocate for the Petitioner.
Mr. S. K. Tambe, AGP for Respondent No. 1.
Mr. S. S. Tope, Advocate for Respondent Nos. 2 to 4. CORAM : S. V. GANGAPURWALA & R. N. LADDHA, JJ.
DATED : 27th AUGUST, 2021.
PER COURT:- .
We have heard Mr. Dhorde, learned senior counsel for the petitioner.
2.
Mr. Tope, learned counsel appears for respondent No. 2 to 4 and submits that the grievance of the petitioner is redressed. The security deposit of Rs. 1.62 Crore is already paid. Remaining amount of Rs. 9.57 Crore is decided to be paid to the petitioner and the Accounts Department is directed to take further steps in the matter. The sale deed is also directed to be executed in respect of 3276.60 square
2 923-wp 5116-2019.odt meters land in exchange at Kanchanwadi and the directions are also given for execution of the registered sale deed. The necessary steps are undertaken.
3.
In the light of the above, the grievance of the petitioner stands redressed. The parties may proceed further as per the letter dated 26.08.2021 placed on record expeditiously. The same is marked as ' X'
for identification.
4.
Writ petition is disposed of. No costs.
( R. N. LADDHA ) ( S. V. GANGAPURWALA ) JUDGE JUDGE P.S.B.