← Library
Bombay High CourtCA/617/2018delay condonatedrejected

Akhtarbi Manjur Jarekari And ANR v. The State Of Maharashtra

2022-11-15Hon'Ble Shri Justice Y. G. Khobragade3 pages

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 922 CIVIL APPLICATION NO.617 OF 2018 IN FAST/12838/2017 WITH CA/621/2018 IN FAST/12842/2017 WITH CA/623/2018 IN FAST/12870/2017 WITH CA/618/2018 IN FAST/12864/2017 WITH CA/619/2018 IN FAST/12854/2017 WITH CA/620/2018 IN FAST/12846/2017 WITH CA/622/2018 IN FAST/12840/2017 AKHTARBI MANJUR JAREKARI AND OTHERS

VERSUS

THE STATE OF MAHARASHTRA ...

Advocate for Applicants : Mr. Sonwane Mahesh R. AGP for Respondents State: Mr. S. R.Yadav-Lonikar

CORAM

: Y. G. KHOBRAGADE, J.

DATE : 15TH NOVEMBER, 2022 ORDER:

1.

Heard Mr. Sonawane, the learned Advocate for the applicants and Mr. S.R. Yadav-Lonikar, learned AGP for the State. 2.

Learned counsel for the applicants vehemently canvassed that, on 23.01.2009, the trial court passed impugned judgment and award in Land Acquisition Reference No. 424/2009 and other connected matters, however, due to poor financial condition, some time is consumed in collecting necessary documents and to arrange required amount for payment of court fees and therefore delay of 2910 days

caused in filing the appeals, which is bonafide and substantial. Hence, prayed for condonation of the same.

3.

The learned AGP has not disputed about the fact of passing of the judgment and award on 23.01.2009 however, he submitted that the applicants have not explained the delay properly and hence, prayed for rejection of the applications.

4.

It is well settled principle of law that the litigant should not be suffered for receiving substantial justice on technical ground and the court should be liberal while condoning the delay, if proper and substantial explanation is given. In the case in hand, it appears that on 23.01.2009, the reference court passed impugned judgment and award under Section 18 of the Land Acquisition Act and the applicants have obtained certified copy of the same on 15.06.2009. However, due to their poor financial condition and as some time is consumed in collecting documents, delay of 2910 days caused. Therefore, in the interest of justice it would be just and proper to condone the delay caused in filing the appeals.

5.

Since the applicants claim for enhancement of compensation and there is delay of 2910 days caused in filing the appeals, so also, though the applicants filed present civil applications along-with first appeals in the year 2017, but again for five years, the applicants did not

bother to circulate the matter. Hence to my mind the applicants will not be entitled for the interest and statutory benefits for the delayed period so also for the period which has been consumed in circulating the matter till date. Accordingly, I proceed to pass the following order:-

O R D E R

i. Civil applications are hereby allowed ii.

The delay of 2910 days caused in filing appeals is hereby condoned. The applicants will not be entitled for interest and statutory benefits for the delayed period as well as till date of this order.

iii.

Registry of this office is directed to register the appeals and place before this Court for further action.

iv.

Copy of the order be placed in appeals so that at the time of final argument, it can be referred.

(Y. G. KHOBRAGADE, J.) JPChavan