← Library
Bombay High CourtCA/9368/2024admittedallowedgrantedrule absolute

Kashinath Chindha Patil And ORS v. The Executive Engineer Hatnoor Project Chopada And ORS

2024-11-29Hon'Ble Shri Justice R. G. Avachat,Hon'Ble Shri Justice Neeraj P. Dhote1 pages

907-CA-9368-24.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 9368 OF 2024 IN FIRST APPEAL NO. 3005 OF 2022 Kashinath Chindha Patil and Others ..APPLICANTS

VERSUS

The Executive Engineer, Hatnur Project Chopda and Others ..RESPONDENTS ....

Mr. V.B. Patil, Advocate for applicants Mr. V.V. Tarde, Advocate for respondent no.1 Mrs. K.B. Patil Bharaswadkar, Addl.G.P. for respondent nos. 2 and 3 Mr. A.A. Suryawanshi, Advocate for respondent no.4 ....

CORAM : R.G. AVACHAT AND NEERAJ P. DHOTE, JJ DATE : 20th DECEMBER, 2024 PER COURT :

1.

Learned counsel for Respondent No.4 has tendered across the bar a copy of affidavit-in-reply, specifically contending that Respondent No.4 has no objection to allow to withdraw the amount of compensation by the applicants in the present application. Further she does not claim any interest in the compensation amount.

2.

In view of above, office shall comply with the order of this Court dated 29th November, 2024.

( NEERAJ P. DHOTE, J. ) ( R.G. AVACHAT, J. ) SSD 1 / 1