Yogesh Dnyandeo Wake v. Through Its General Manager
1 32-Arb-5-23.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD ARBITRATION APPLICATION NO.5 OF 2023 GS PEB AND CIVIL WORKS PVT. LTD. THROUGH ITS AUTHORISED SIGNATORY YOGESH DNYANDEO WAKE
VERSUS
M/S VARROC ENGINEERING LTD. THROUGH ITS GENERAL MANAGER ...
Advocate for Applicants : Mr. A.D. Sonkawade, Advocate h/f Mr. Rajesh H. Mewara Advocate for Respondent : Mr. Anil S. Gaikwad ...
CORAM : NITIN B. SURYAWANSHI, J.
DATE : 07th AUGUST, 2023 PER COURT :
1.
By order dated 05/07/2023, this Court directed the Registry to obtain consent of Justice Shri. V. K. Jadhav (Retired), for conducting arbitration in the present matter. On 18/07/2023, the consent is received by the Registry.
2.
In that view of the matter, Justice Shri. V. K. Jadhav (Retired), is appointed as Arbitrator to resolve the dispute between the parties. Application is accordingly disposed of. (NITIN B. SURYAWANSHI, J.) SVH