Dharma Ramu Pawar And Others v. The State Of Maharashtra And Others
(1) WP No.5446/2017
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD.
WRIT PETITION NO. 5446 OF 2017 Dharma Ramu Pawar & ors.
Petitioners.
Versus
State of Maharashtra and others.
Respondents.
*** Mr. S.B. Solanke, Advocate for the petitioners. Mr. S.G. Karlekar, A.G.P. for the State/respondent Nos.1 to 3. *** CORAM :
S.V. GANGAPURWALA & SUNIL K. KOTWAL,JJ.
Dated :
2nd August , 2018.
FINAL ORDER :- .
Mr. Solanke, the learned Counsel for the petitioners submits that possession of the land of the petitioner is taken way back in the year 2003. the notices were also issued. On 19.03.2013, a notice under Section 9 of the Land Acquisition Act, 1894 was also issued. No award is passed. The learned Counsel submits that the respondents be directed to commence acquisition proceeding as per the new Act.
(2) WP No.5446/2017 2.
The learned Additional Government Pleader appears for respondent Nos.1 to 3.
3.
Considering the fact that steps are not taken for acquisition, we direct the respondents to commence the acquisition proceeding within a period of four months from today and shall complete it within the time stipulated under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
4.
Writ Petition is accordingly disposed of. No costs. ( SUNIL K. KOTWAL) ( S.V. GANGAPURWALA) JUDGE JUDGE vdd/