Icici Lombard General Insurance Co Ltd v. Sheetal Ashok Mane And ORS
40-CA-4881-25++.odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD 40 CIVIL APPLICATION NO. 4881 OF 2025 IN FAST/12270/2024 WITH CIVIL APPLICATION NO. 5821 OF 2024 IN FAST/12270/2024 WITH CIVIL APPLICATION NO. 5822 OF 2024 IN FAST/12270/2024 ICICI LOMBARD GENERAL INSURANCE CO LTD
VERSUS
SHEETAL ASHOK MANE AND ORS ....
Mr. R. H. Dahat, Advocate for the applicant Mr. S. S. Dargad and A. J. Mantri, Advocates for respondent Nos.1 to CORAM : S. G. CHAPALGAONKAR, J.
DATE : 02.05.2025 PER COURT :- .
Heard learned Advocates appearing for respective parties.
2.
Applicant seeks to condone the delay of 184 days caused in filing the appeal.
3.
Perused the reasons as stated in the application, the delay is occasioned on account of administrative exigency. Hence, sufficient cause is made out to condone the delay. In result, following order is passed:
::ORDER::
.
Civil application is allowed.
(( 2 )) 40-CA-4881-25++ 2.
Delay of 184 days caused in filing appeal is condoned. 3.
Appeal be registered subject to removal of office objections, if any.
IN APPEAL .
Heard.
2.
Issue notice to respondents, returnable on 11.07.2025. Mr. S. S. Dargad and A. J. Mantri waive notice for respondent Nos.1 to 3. 3.
Call for Record and Proceeding.
APPLICATION FOR WITHDRAWAL OF AMOUNT .
Application for withdrawal of amount to be considered at the time of admission along with after receipt of R & P. STAY APPLICATION .
Heard learned Advocate appearing for the applicant. He submits that the entire amount as per the award passed has been deposited with the Registry of this Court. His statement is supported by office endorsement.
2.
In that view of the matter, application is allowed in terms of prayer clause (B) and disposed of.
[ S. G. CHAPALGAONKAR, J. ] HRJadhav