The Executive Engineer, Krishna Khore Division, O.Bad v. Subhash Namdeo Bhorade And Another
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD (1) 6102-16cagr delay 914 CIVIL APPLICATION NO. 6102 OF 2016 IN FAST/13667/2016 THE EXECUTIVE ENGINEER, KRISHNA KHORE DIVISION, O'BAD
VERSUS
EKNATH BHANUDAS BHORADE AND ANOTHER ...
Advocate for Applicant : Mr.Patil Ruturaj C.
AGP for Respondent State: Mr.S.N.Morampalle Mr.Manoj Dond Patil, Adv., h/f Mr.Shinde Chandrakant K., Adv. For Resp.No. 1 Respondent no.2 served.
...
WITH CA/6068/2016 IN FAST/13400/2016 WITH CA/6076/2016 IN FAST/13715/2016 WITH CA/6078/2016 IN FAST/13712/2016 WITH CA/6089/2016 IN FAST/13721/2016 WITH CA/6100/2016 IN FAST/13670/2016 WITH CA/6112/2016 IN FAST/13679/2016 WITH CA/6118/2016 IN FAST/13688/2016 ...
CORAM : P.R. BORA, J.
Dated: July 19, 2016 ...
PER COURT :- 1.
Heard. Delay of 333 days has occurred in filing the present appeals. Learned Counsel appearing for the respondent i.e. original claimant does not have any AGP/-
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD (2) 6102-16cagr delay objection for condonation of delay. In view of the submission so made, and for the reasons stated in the applications, the delay is condoned. The appeals be registered in accordance with law. Civil Applications stand disposed of.
( P.R. BORA, J. ) ...
AGP/-