IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 3 CIVIL APPLICATION NO. 4648 OF 2025 IN FA/1910/2022 The Executive Engineer Nimna Dudhna Project, Selu Dist Parbhani And Ors.
....Applicants
VERSUS
Ramesh Pralhadrao Nirval And Ors.
.....Respondents .....
WITH CIVIL APPLICATION NO. 4651 OF 2025 IN FA/3710/2017 WITH CIVIL APPLICATION NO. 4652 OF 2025 IN FA/1911/2022 WITH CIVIL APPLICATION NO. 4650 OF 2025 IN FA/4485/2017 WITH CIVIL APPLICATION NO. 4653 OF 2025 IN FA/1939/2022 WITH CIVIL APPLICATION NO. 4649 OF 2025 IN FA/1909/2022 .....
Mr. Arora Shyam C., Advocate for the Applicants Mr. K. M. Kakade, Advocate for the Respondents ....
CORAM
:
NEERAJ P. DHOTE, J.
DATE :
23.04.2025 PER COURT :
1.
These are the Applications by the Acquiring Body in disposed off Appeals for extension of time to deposit the amount as directed by the National Lok-Adalat on 03/03/2024.
2.
It is submitted by the learned Advocate for the Acquiring Body that, one [1] year period granted to deposit the amount by the Acquiring Body has come to an end in March - 2025. He submits that, now, the amount is ready with the Acquiring Body for depositing in the Court.
3-CA-4648-2025.odt 3.
The learned Advocate for the Respondents - Claimants is present.
4.
In view of the above submission, the Applications are allowed and the time to deposit the amount is further extended till one [1] weeks onward today. Civil Applications stand disposed off accordingly.
[NEERAJ P. DHOTE, J.] Sameer/April-2025 Signed by: Md. Sameer Q.