IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 14368 OF 2018 IN FA/1868/2019 Executive Engineer, Patbandhare Majbutikarn Division Omerga Thr. Exe Engineer, Osmanabad. .....Applicant

VERSUS

Shekhar Sharanyya Swami And Ors.

.....Respondents .....

Mr. Avishkar S. Shelke, Advocate for the Applicant - Acquiring Body Mr. Patil Laxmikant C., Advocate for Respondent No.1 Ms. M. L. Sangit, AGP for Respondent Nos.2 and 3 .....

CORAM

:

NEERAJ P. DHOTE, J.

DATE :

04.11.2025 PER COURT :

1.

This is an Application by the Acquiring Body seeking stay to the execution and implementation of the Judgment and Award in Land Acquisition Reference No.400/2013, decided on 05/02/2025 by the learned Reference Court at Omerga.

2.

Heard both the sides.

3.

The Acquiring Body i.e. Applicant has deposited the entire amount under the Award. Hence, the Application is allowed in terms of Prayer Clause - 'B' and the same stands disposed off accordingly. [NEERAJ P. DHOTE, J.] Sameer/November-2025