Bombay High CourtCA/8044/2018disposed offdismissed for default

Ex. Engineer, Irrigation Project Majbutikarn Div. Omerga (Now Under The M.K.V.D.C., Ltd Pune) v. Shanteshwar Vishwanath Barbade And ORS

2019-07-19Hon'Ble Smt. Justice Vibha Kankanwadi2 pages

1001-ca-8044-18 (delay).doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 1001 CIVIL APPLICATION NO.8044 OF 2018 IN FAST/13749/2018 EX. ENGINEER, IRRIGATION POJECT MAJBUTIKARN DIV. OMERGA (NOW UNDER THE M.K.V.D.C

VERSUS

SHANTESHWAR VISHWANATH BARADE AND ORS ...

Advocate for Applicant : Mr. Sangle Shirish G. AGP for Respondents/State : Mr. R.B. Bagul Advocate for Respondent No.1 : Mr. Patil Laxmikant C. ...

CORAM : SMT. VIBHA KANKANWADI, J.

DATE : 19th JULY 2019 ORDER :

.

Present application has been filed for getting the delay of 1726 days condoned in filing First Appeal. Acquiring body intends to challenge the judgment and award passed by the Reference Court. Learned Advocate appearing for original claimants strongly objects to the application on the ground that the delay is huge and inordinate and has not been properly explained.

2.

Taking into consideration the steps those have been taken as narrated in the application, it can be said to be the genuine efforts on the part of the acquiring body to seek permissions, sanctions etc. Under such circumstance, the delay stands condoned.

1001-ca-8044-18 (delay).doc 3.

Civil Application stands allowed and disposed of accordingly.

4.

Registry to verify and register the First Appeal and place it for further consideration on 30.01.2020.

( Smt. Vibha Kankanwadi, J. ) Shubham/