Narendra Bapusaheb Patekar And Another v. The State Of Maharashtra And Others
wp4023-13 -1-
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD WRIT PETITION NO. 4023 OF 2013 NARENDRA BAPUSAHEB PATEKAR AND ANOTHER
VERSUS
THE STATE OF MAHARASHTRA AND OTHERS ...
Advocate for Petitioners : Mr.Manoj Thorbole h/f Narwade Narayan B.
AGP for Respondents: Mr.S.G.Karlekar Advocate for Respondents : Mr.V.C.Patil h/f Godsay Satish M. For R/2,3 ...
CORAM : S.V.GANGAPURWALA & A.M.BADAR,JJ.
DATED : 16TH FEBRUARY,2016 PER COURT :- We have heard learned counsel for the petitioner. The learned counsel for the respondents submits that the construction of transmission tower is complete.
2] In view of that, no relief can be granted to the petitioner. The petitioner has remedy available for compensation or otherwise. 3] Writ Petition is disposed of. No costs.
(A.M.BADAR,J.) (S.V.GANGAPURWALA,J.) umg/