Shaikh Azhar Shaikh Haider Patel And ANR v. The Executive Engineer, Minor Irrigation Division No.1, Aurangabad And ORS
908- C.A.7391.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 908 CIVIL APPLICATION NO.7391 OF 2018 IN FA/335/2016 SHAIKH AZHAR SHAIKH HAIDER PATEL AND ANR
VERSUS
THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION NO.1, AURANGABAD AND ORS ...
Advocate for Applicants : Mr. A. N. Ansari AGP for Respondent No.2: Mr. A. B. Chate Advocate for respondent No.1 : Mr. N. H. Helkate h/f Reddy Ranjana D.
....
CORAM : S. G. DIGE, J.
DATE : 03.08.2022 PER COURT :- Heard learned counsel for the applicants, learned counsel for the respondent No.1 and learned AGP. 2.
Learned counsel for the applicants submits that respondent No.1 has deposited the award amount before this Court, but it is deposited without making proper calculations. Hence he requested to give direction to respondent No.1 to deposit the amount by making proper calculations. 3.
Learned counsel for respondent No.1 submits that he will go through the chart prepared by the applicants and if there is deficient amount, it will be deposited.
908- C.A.7391.odt 4.
Considering the submissions of both the learned counsel, the application is allowed and disposed of.
( S.G. DIGE,) JUDGE ysk