The Executive Engineer, Osmanabad Medium Project Division, Osmanabad Thr M.K.V.D.C. Pune And ORS v. Amol Jayram Gunjal And ORS
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 918 CIVIL APPLICATION NO. 7878 OF 2016 IN FAST/14206/2016 THE EXECUTIVE ENGINEER, OSMANABAD MEDIUM PROJECT DIVISION, OSMANABAD THR M.K.V.D.
VERSUS
AMOL JAYRAM GUNJAL AND ORS ...
Advocate for Applicant : Mr.Gaddime Arvind N. Advocate for respective respondent : Mr. E.S.Murge ...
CORAM : P.R. BORA, J.
Dated: June 07, 2017 ...
PER COURT :- 1.
Heard learned Counsel for the applicant and learned Counsel appearing for the respondents i.e. original claimants. 2.
Delay of 542 days has occurred in filing the appeals. Though learned Counsel for the claimants has opposed for condonation of delay, stating that no cogent reasons are assigned for condonation of delay, for the reasons stated in the application which, according to me, are just and sufficient, the delay is condoned. Civil Application stands disposed of. The Appeal be registered in accordance with law.
3.
After registration of the appeal, issue notice to the respondents returnable after four weeks. S.O. to 5.7.2017. ( P.R. BORA, J. ) ...
agp/-