IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 59 WRIT PETITION NO. 2337 OF 2024 WITH CIVIL APPLICATION NO. 4641 OF 2024 IN WP/2337/2024 Meena Narsingrao Pawar And Aruna Baburao Badde.

VERSUS

The State Of Maharashtra Through Principal Secretary And Others ...

Advocate for the Petitioner : Mr. Patil N.P. Jamalpurkar AGP for Respondents: Mr. N S Tekale Advocate for Respondent 5 : Mr. M.S. Taur ...

CORAM : SMT. VIBHA KANKANWADI & S. G. CHAPALGAONKAR, JJ.

Dated : May 06, 2024 PER COURT :- 1.

Present petition is filed for directions to respondent nos.2 and 3 to grant approval to the appointments of the petitioners as Higher Secondary Teachers from the date of their initial appointments namely 17.06.2013 and consequential prayer was made.

2.

By filing civil application no.4641 of 2024 petitioners have prayed for directions to respondents to implement the order dated 16.4.2024 passed by the Hon'ble Minister in appeal thereby fact has been brought on record that in the appeal filed by the present petitioners, the Hon'ble Minister has decided the status and grievance of the petitioners.

wp 2337.24.odt 3.

In similarly situated matter writ petition no.3804 of 2024 decided on 16.4.2024 this Court has given directions. Similarly, now in view of the fact that already the Hon'ble Minister, Other Backward Bahujan Welfare Department has the passed order on 13.4.2023 which was in favour of the petitioners, the question is only in respect of implementation of the same.

4.

Learned AGP after waiting notice for respondent nos.1 to 4 had made statement in writ petition no.3804 of 2024 that implementation would be done within a period fo three weeks. 5.

Taking into consideration the order passed by the Hon'ble Minister, which can be said to have been attained finality, now the implementation has to be done in view of the statement made. The steps those are required for implementation of the said order dated 13.4.2023 be undertaken within a period of three (3) weeks from today by respondents no.1 to 4.

6.

Accordingly, Writ Petition and Civil application stands disposed off.

( S. G. CHAPALGAONKAR, J. ) ( SMT. VIBHA KANKANWADI, J. ) ...

aaa/-