IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 951 WRIT PETITION NO. 11932 OF 2014 THE EXECUTIVE ENGINEER, UPPER PENGANGA PROJECT DIVISION NO.8, NANDED ....Petitioner

VERSUS

THE STATE OF MAHARASHTRA AND OTHERS .....Respondents Mr. B. R. Surwase, Advocate for the petitioner Mr. R. K. Ingole, APP for the respondents/State CORAM : ABHAY J. MANTRI, J.

DATE : 01st OCTOBER, 2025 PER COURT :

1.

The learned advocate for the petitioner submitted that this court has already passed the order dated 24-02-2015 in WP/9447/2014 with connected matters, thereby dismissing the writ petitions on identical issues. The facts in this petition are similar, i.e. the parties had entered into a compromise before the Lok Adalat held on 02,08.2009. He has tendered the said order across the bar. The same is taken on record and marked 'X' for identification purposes. The said order covers the issue in the case at hand. So, he urged passing the same order in the case at hand.

2.

I have gone through the record and order produced before me by the learned advocate for the petitioner. I find substance

(2) 951wp11932.14.odt in the contention of the learned advocate for the petitioner in that regard.

3.

In view of the observations made in the order dated 2402-2015 in WP/9447/2014, the writ petition stands dismissed. [ABHAY J. MANTRI, J.] VishalK/951wp11932.14.odt