IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 931 CIVIL APPLICATION NO. 7318 OF 2017 IN FA/559/2017 ASHALATA PURBHAJI JONDHALE AND OTHERS

VERSUS

EXECUTIVE ENGINEER, M.S.E.D.C. LTD OFFICE AT JINTUR ROAD, PARBHANI ...

Advocate for Applicant : Mr. Mayure Pramod C. Advocate for Respondent : Mr. D.P. Deshpande.

CORAM

: K. L. WADANE, J.

DATE :

21st September, 2017 ORDER:

1.

Heard learned counsel for the applicants as well as learned counsel for the respondent.

2.

This is an application for withdrawal of amount of compensation deposited by the respondent in this Court. Learned counsel for the respondent opposes the payment of compensation to the applicants/claimants on the grounds that, there is delay for about 03 months for filing first information report, secondly; no oral evidence is adduced on behalf of the claimants to establish the whole negligence on the part of the truck driver and thirdly; the quantum of compensation. 3.

I have gone through the report submitted by the concerned medical officer to the concerned police station, from which, it appears that the factum of the accident was promptly reported to the concerned police station, in which there is reference of the accident between two vehicles.

4.

Learned counsel for the applicants/claimants 1/2

931 7318.odt submits that, the respondent has not denied the factum of the accident. Learned counsel for respondent submits that, such defence of the respondent is an alternate defence. Initially, the respondent has denied the factum of the accident.

5.

Presently the award is in favour of the applicant and for the reasons recorded in the judgment by the learned Tribunal, at this stage, there is no hurdle to pay at least 50 % amount of compensation to the applicants/claimants, since the appellant is contesting the appeal on the ground of quantum also. 6.

In such circumstances, the applicants are permitted to withdraw 50 % amount of compensation deposited in this Court, on undertaking that, in the event of adverse orders are passed in the appeal, then they shall deposit the amount of compensation within a period of 12 weeks.

7.

Civil Application is disposed of.

(K. L. WADANE, J.) mkd 2/2