← Library
Bombay High CourtCA/11919/2019delay condonatedrejected

The Oriental Insurance Co. Ltd., Thr Its Divisional Manager, Aurangabad v. Sudam Zungaji Todmal And ORS

2020-12-10Hon'Ble Shri Justice V.L. Achliya2 pages

1 [914-CA 11919.2019 in F.A.St. 14554.2019]

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 914 CIVIL APPLICATION NO.11919 OF 2019 IN FAST/14554/2019 THE ORIENTAL INSURANCE CO. LTD., THR ITS DIVISIONAL MANAGER, AURANGABAD AND ORS

VERSUS

SUDAM ZUNGAJI TODMAL AND ORS.

......

Mr. A.G.Kanade, Advocate for Applicant.

Mr. V.S.Bedre, Advocate for R - 3.

......

CORAM : V.L.ACHLIYA, J.

DATE : 10/12/2020 ......

ORAL ORDER :

1.

The applicant has moved this application seeking condonation of 224 days delay caused in filing Appeal for the reasons set out in detail in the application. 2.

Heard learned counsel for applicant and counsel representing respondent No. 3. Respondent Nos. 1 and 2 though served, absent.

3.

On due consideration of submissions advanced in the light of unchallenged unvontroverted pleadings made in the application seeking condonation of delay and consequences to follow if delay is not condoned, I am of the view the delay deserves to be condoned. Accordingly, the application is allowed in terms of

2 [914-CA 11919.2019 in F.A.St. 14554.2019] prayer clause 'B'. Delay is condoned. Appeal be registered.

[V.L.ACHLIYA] JUDGE KNP