-:(1):- FARAD CONTINUATION SHEET NO.

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD.

Office Notes, Office Memoranda of Coram, appearance, Court's orders or directions and Registrar's orders.

Court's or Judge's orders.

CIVIL APPLICATION NO. 6084 OF 20165 IN FAST/15441/2015 THE NEW INDIA ASSURANCE CO.LTD THR MANAGER (LEAL HUB)AURANGABAD AND OTHERS

VERSUS

PRATIBHA MANGESH MALI AND OTHERS ...

Advocate for Applicants : Mr. M. M. Ambhore.

Advocate for Respondent Nos.1 to 4: Mr. L. V. Sangit. *** CORAM: T. V. NALAWADE, J.

DATED:

12th JANUARY, 2016.

PER COURT:

1.

The application is filed for condonation of delay of 35 days caused in filing appeal against Judgment and Award of Tribunal. Learned counsel for Insurance Company and learned counsel for claimant are heard. Other respondents are served. In view of the contents of the application and the submissions made this Court holds that sufficient cause is shown. Delay is condoned. Application is allowed and disposed of.

[T. V. NALAWADE, J.] Dt.12/01/2016.

ans/6084