Machindra Baliram Dhane v. The Ex. Engineer, Osmanabad Minor Irrigation Project Div. Osmanabad And Others
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO.6253 OF 2021 IN FIRST APPEAL ST. NO.31130 OF 2019 Machindra s/o Baliram Dhane ... APPLICANT
VERSUS
The Executive Engineer, Osmanabad Minor Irrigation Project Division and others ... RESPONDENTS .......
Mr. V.B. Deshmukh, Advocate for applicants Mr. A.D. Gadekar, Advocate for respondent No.1. Mr. Y.G. Gujarathi, A.G.P. for respondents No.2 and 3 .......
CORAM :
R. G. AVACHAT, J.
DATE :
5th AUGUST, 2021 PER COURT :
Heard. For the reasons given in the application, the applicant is permitted to withdraw 75% of the amount deposited. 50% of the amount be paid on furnishing usual undertaking and 25% of the amount be paid on furnishing solvent surety/ security. Application is disposed of. ( R. G. AVACHAT ) JUDGE fmp/-