The Ex. Engineer, Upper Penanga Project No. 6 Nanded v. Prakash Dattatraya Kulkarni And ORS
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 52 CIVIL APPLICATION NO.176 OF 2019 IN FA/2673/2019 THE EX. ENGINEER, UPPER PENANGA PROJECT NO. 6 NANDED
VERSUS
PRAKASH DATTATRAYA KULKARNI AND ORS ...
Advocate for Appellants : Mr.Anant D. Gadekar Advocate for Respondent No.1 : Mr.M.D. Godhamgaonkar AGP for Respondents No.2 & 3 : Mr.R.B.Bagul ...
CORAM : K. K. SONAWANE, J.
Date: January 13, 2020 ...
PER COURT :- 1.
The learned counsel for the applicant-Acquiring Body submits that as per order passed by this Court dated 26.07.2019, entire decreetal amount has been deposited on behalf of the applicantAcquiring Body. Therefore, stay may be continued. 2.
In view aforesaid submission, interim relief granted earlier to continue. The execution and implementation of the impugned Judgment and award is stayed till further orders. 3.
In view of above, application stands disposed of. ( K. K. SONAWANE, J. ) SPT