The Ex. Engineer Construction Central Railway Solapur Division, Solapur v. Limbraj Narayan Bolange And ANR
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO.6522 OF 2019 IN FIRST APPEAL (ST.) NO.15518 OF 2019 (The Executive Engineer (Construction), Central Railway Solapur Division, Solapur Vs. Limbraj Narayan Bolange and another) ---- Mr. A.D. Soman, Advocate holding for Mr. D.V. Soman, Advocate for the applicant Mr. S.N. Morampalle, A.G.P. for the respondent/State ---- CORAM : MANGESH S. PATIL, J.
DATE : 13.12.2019 PER COURT :
This is an application for condonation of delay filed by the Acquiring Body seeking to prefer an appeal challenging the judgment and award passed by the Reference Court under Section 18 of the Land Acquisition Act.
2.
The respondent/original claimant has been duly served but has not appeared.
3.
For the reasons mentioned in the application and for want of any demur, the delay is condoned. The application is accordingly allowed. The appeal be registered.
[MANGESH S. PATIL] JUDGE npj/ca6522-2019