The Executive Engineer, Medium Project Division, Dhule v. Sindhubai Chaitram Patil And Others
5339.15ca -1-
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 5339 OF 2015 IN FIRST APPEAL (ST.) NO. 16122 OF 2014 The Executive Engineer, Medium Project Division, Dhule ...Applicant versus Budha Mukunda Sonawane (dead) through L.Rs.
Vasant Budha sonawane & ors.
...Respondents
WITH C.A. NO. 5351/2015 IN F.A.ST. NO. 16125/2014 C.A. NO. 5355/2015 IN F.A.ST. NO. 16108/2014 .....
Mr. S. S. Chillarge, Advocate for applicant. Mr. V. D. Gunale, Advocate for respondent/caveator. Mr. G. R. Ingole, A. G. P. for respondent/State. .....
CORAM : N.W. SAMBRE, J.
DATE : 30th JUNE, 2015 ORAL ORDER :
These applications for condonation of delay are opposed by the claimants, as according to the claimants-land owners, delay is inordinate and not explained.
2.
It is brought on record by the applicants that the delay in preferring the applications and appeals is caused because of
5339.15ca -2administrative reasons.
3.
In my opinion, there is sufficient cause brought before this Court. As such, delay is condoned. The applications are allowed.
[ N.W. SAMBRE, J. ] Tupe/30.06.15