The Executive Engineer, Medium Project Division, Dhule v. Sattu Dashrath Thelari And Yadav Dhondu Thelari And Others
6050.15ca -1-
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 6050 OF 2015 IN FIRST APPEAL (ST.) NO. 16162 OF 2014 The Executive Engineer, Medium Project Division, Dhule ...Applicant versus Sattu Dashrath Thelari & ors.
...Respondents
WITH C.A. NO. 6054/2015 IN FAST NO. 16171/2014 .....
Mr. S. S. Chillarge, Advocate for applicant. Mr. V. D. Gunale, Advocate for respondent/caveator. Mr. G. R. Ingole, A. G. P. for respondent/State. .....
CORAM : N.W. SAMBRE, J.
DATE : 30th JUNE, 2015 ORAL ORDER :
These applications for condonation of delay are opposed by the claimants, as according to the claimants-land owners, delay is inordinate and not explained.
2.
It is brought on record by the applicants that the delay in preferring the applications and appeals is caused because of administrative reasons.
6050.15ca -23.
In my opinion, there is sufficient cause brought before this Court. As such, delay is condoned. The applications are allowed.
[ N.W. SAMBRE, J. ] Tupe/30.06.15