The Executive Engineer, Medium Project, Osmanabad v. Venkat Govind Jadhav And Others
918-ca.15997.13.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
BENCH AT AURANGABAD.
918 CIVIL APPLICATION NO. 10364 OF 2014 IN FAST/16917/2014 THE EXECUTIVE ENGINEER, MEDIUM PROJECT, OSMANABAD
VERSUS
VENKAT GOVIND JADHAV AND OTHERS ...
Advocate for Applicant : Mrs. Sunita Shelke, h/f Mr. G. B. Rajale. Advocate for Respondent No.1 : Mr. Pravin B. Rakhunde. AGP for Respondent Nos.2 & 3: Mr. S. N. Morampalle. ...
CORAM :
SHRIKANT D. KULKARNI, J.
DATE :
07th April, 2022.
P.C.:
.
It is an application for condonation of delay moved by the applicant/acquiring body.
Heard Mrs Sunita Shelke, holding for Mr. G. B. Rajale, learned counsel for applicant, Mr. Rakhunde, learned counsel for claimants and Mr. Morampalle, learned AGP for respondent Nos.2 and 3. There seems to be delay of 747 days in preferring the first appeal. However, by looking to the nature of dispute and for the reasons stated in the application for condonation of delay, paragraphs 8 to 10, the delay needs to be condoned. Hence, the following order is passed:
918-ca.15997.13.odt
O R D E R
I.
The application is hereby allowed in terms of prayer clause (B).
II.
The Registry to make scrutiny of the appeal as per the procedure and it be numbered and placed before the Court for admission.
III.
The civil application is accordingly disposed of. [ SHRIKANT D. KULKARNI, J. ] nga