← Library
Bombay High CourtCA/9161/2016disposed offdismissed for default

Executive Engineer, Vishnupuri Project Div. Nanded Now Lendi Project Div Degloor Under Gmidc And Or v. Shrirang Govindrao Patil And ORS

2017-12-07Hon'Ble Shri Justice K. K. Sonawane1 pages

1 914-CA-9147-16

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 914 CIVIL APPLICATION NO. CA/9147/2016 IN FAST/17956/2016 EXECUTIVE ENGINEER, VISHNUPURI PROJECT DIV. NANDED NOW LENDI PROJECT DIV DEGLOOR

VERSUS

SURYAJI GOVINDRAO PATIL AND ORS ...

Advocate for Applicants : Mr. B.R. Survase AGP for co-appellants: Mr. S.R. Yadav Advocate for Respondents - ori. claimants : Mr. S.V. Kurundkar .......

WITH CA/9143/2016 IN FAST/17942/2016 WITH CA/9153/2016 IN FAST/17953/2016 WITH CA/9158/2016 IN FAST/17939/2016 WITH CA/9161/2016 IN FAST/17960/2016 CORAM : K.K. SONAWANE, J.

DATED : 07TH DECEMBER, 2017.

Order :- 1.

Heard learned counsel for appearing parties. Learned counsel for the applicant -Acquiring Body submits that pursuant to order passed by this Court, the applicant - Acquiring Body has deposited the amount in this Court. He further submits that by continuing stay granted earlier pending the appeals, present civil applications may be disposed of. Learned counsel for respondents-original claimants has no objection for the same.

2.

In view aforesaid submissions, stay granted by this Court under order dated 11th August, 2016 for execution and implementation of the impugned award in the present appeals is hereby made confirmed and absolute till final decision of the appeal. The civil applications stand disposed of accordingly.

[ K. K. SONAWANE ] JUDGE MTK.