Executive Engineer, Sina Kolegaon Project Division, Paranda And Others v. Angad Shivdas Chaugale And Another
G.A.Ghule [P.A.] 1/1 ca 12322.15 in fast 17759.15 with ca 12324.15 (i order - delay) (Sr.No.1031).sxw
IN THE HIGH COURT OF JUDICATURE AT BOMBAY.
BENCH AT AURANGABAD.
Civil Appellate Jurisdiction.
CIVIL APPLICATION NO. 12322 OF 2015.
IN FIRST APPEAL (STAMP)NO.17759/2015.
EXECUTIVE ENGINEER, SINA KLEGAON PROJECT DIVISION, PARANDA AND OTHERS.
VERSUS
ANGAD SHIVDAS CHAUGALE AND ANOTHER.
Appearance => Mr. Sanjaykumar B. Bhosale, Advocate for the Applicants. Mr. Tanawade, Advocate for Respondent Nos. 1 and 2. Mr. D.V. Tele, Additional Government Pleader for the State. Coram :
S.V. Gangapurwala, J.
Date :
1st October, 2015.
Per Court :- Issue notice to Respondent Nos. 1 and 2, returnable after 10 weeks.
[2] Mr. Tanwade, learned counsel accepts the notice for Respondent Nos. 1 and 2. It is submitted that delay is not properly explained.
[3] Considering the reasons given in the Application and as averments made in the application are not controverted, in the light of that delay is condoned. Civil Application is disposed of. (S.V. GANGAPURWALA, J.)