The Executive Engineer, Irrigation Project Majbutikaran Division, Omerga And Others v. Nagesh Rangrao Waddare
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
BENCH AT AURANGABAD CIVIL APPLICATION NO.10415 OF 2015 IN FIRST APPEAL STAMP NO.18245 OF 2015 Executive Engineer, Irrigation Project Majbutikaran Division, Omerga and others ...
APPLICANTS
VERSUS
Nagesh Rangrao Waddare ...
RESPONDENT .....
Shri A.N. Gaddime, Advocate for applicants Shri A.B. Kale, Advocate for respondent .....
CORAM:
R.M. BORDE AND A.I.S. CHEEMA, JJ.
DATED:
11th December, 2015.
ORAL ORDER :
1.
This is an application seeking condonation of delay of 353 days occurred in presenting the First Appeal. For the reasons recorded in the application, the application deserves to be allowed and same is allowed. Delay of 350 days occurred in presenting the First Appeal is condoned.
(A.I.S. CHEEMA, J.) ( R.M. BORDE, J.) fmp/ca10415.15