The Ex. Engineer, Irrigation Project Strengthening Div. Omerga And ORS v. Kamalakar Gunda Jadhav
2024:BHC-AUG:5395 (1) 15ca7265.22
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 15 CIVIL APPLICATION NO. 7265 OF 2022 IN FA/3760/2022 WITH CIVIL APPALICATION NO. 7267/2022 IN FAST/17291/2020 WITH CIVIL APPLICATION NO.7269/2022 IN FA/3759/2022 THE EX. ENGINEER, IRRIGATION PROJECT STRENGTHENING DIV. OMERGA AND OTHERS VS KERBA GUNDA JADHAV Ms. Sunita Shelke, Advocate for the applicant Ms. M. L. Sangit, AGP for the respondents/State Mr. L. C. Patil, Advocate for the respondent CORAM :
S. G. MEHARE, J.
DATE :
08th MARCH, 2024 P. C.
1.
Heard respective counsels for the parties.
2.
Considering the grounds mentioned in the appeal, it appers that the appellants have good case on merits. The appellants have deposited the compensation amount. Hence, the following order:-
(2) 15ca7265.22
ORDER
i] Applications are allowed.
ii] The order granting ad-interim relief dated 0112-2022 is confirmed till conclusion of the appeal. [S. G. MEHARE, J.] VishalK/15ca7265.22