25 CIVIL APPLICATION NO.7241 OF 2022 IN FAST/18207/2020 Parasram Radhakisan (died) Thr Lrs Kadubai And Ors

Versus

The Ex. Engineer, Minor Irrigation Div. Jalna And Ors .....

Shri. Vilas M. Humbe, Advocate for the Applicants Shri. D. J. Patil, AGP for Respondent Nos.2 & 3 .....

CORAM : NEERAJ P. DHOTE, J.

Dated : MAY 05, 2025 PER COURT :- .

This is the Application by the Orig. Claimants for condonation of 237 days delay in preferring the First Appeal for further enhancement of compensation amount under the Land Acquisition Act. 2.

It is submitted by the learned Advocate for the Applicants that due to financial constraints, the Applicants could not prefer the Appeal within the stipulated time. He submits that the delay may be condoned and the Application may be allowed.

3.

None for Respondent No.1 - Acquiring Body, though served. 4.

The learned AGP for Respondent Nos.2 and 3 / State submits that appropriate orders may be passed.

5.

On hearing the learned Advocate for the Applicants and the learned AGP for the State and for the reasons mentioned in paragraph

nos.6 of the Application, the Application is allowed in terms of prayer clause 'B'. The Applicants shall not be entitled to interest and statutory benefits for the aforesaid delayed period. Copy of this order be kept in the order sheet of the Appeal Memo. Application stands disposed off accordingly.

( NEERAJ P. DHOTE, J. ) GGP Signed by: Gajanan G. Punde Designation: PA To Honourable Judge Date: 06/05/2025 20:20:53