The Executive Engineer, Dhule Medium Project, Dhule v. Sahadu Dhula Akhade And Another
935.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 935 CIVIL APPLICATION NO. 12413 OF 2015 IN FAST/19222/2015 WITH CA/12405/2015 IN FAST/19424/2015 WITH CA/12407/2015 IN FAST/19433/2015 WITH CA/12409/2015 IN FAST/19430/2015 WITH CA/12411/2015 IN FAST/19427/2015 THE EXECUTIVE ENGINEER, DHULE MEDIUM PROJECT, DHULE
VERSUS
GULJARSING RAJESING GIRASE AND ANOTHER ...
Advocate for Applicant : Mr. Pawar Ajay D.
AGP for Respondent No.2: Mr. S. S. Dande Advocate for Respondent No.1 : Mr. Ajeet B. Kale
CORAM
: K. L. WADANE, J.
DATE :
7th September, 2017 ORDER:
1.
Heard.
2.
Theses are applications for condonation of delay caused in filing of the first appeals. From the grounds stated in the applications, it appears that the delay is caused due to procedural aspect and administrative difficulty.
3.
Looking to the facts and circumstance of the case, the appellant has to follow the procedure for filing the appeal and after decision to file the appeal, came to the Court.
4.
In view of the above, for the reasons stated in the applications, the delay in filing the first appeals is hereby condoned. The Civil Applications for
935.odt condonation of delay are disposed of. Appeals be registered.
5.
In first appeals, issue notice to the respondents. Mr. Kale, the learned counsel waives notice for respondents/claimants. Learned AGP waives notice for respondent-State in all the matters. 6.
The learned counsel for the appellant submits that the other companion appeals are admitted by this court. Hence Admit.
7.
Call for record and proceedings.
(K. L. WADANE, J.) JPC