The Executive Engineer, Irrigation Project Majbutikarn Division, Omerga And Others v. Shrimant Krushna Narwade And Others
(1) C. A. No. 9644 of 2015 & Group
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
AURANGABAD BENCH, AT AURANGABAD.
CIVIL APPLICATION NO. 9644 OF 2015 IN FAST/19753/2015 WITH CA/9646/2015 IN FAST/19756/2015 WITH CA/9648/2015 IN FAST/19759/2015 WITH CA/9652/2015 IN FAST/19750/2015 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT MAJBUTIKARN DIVISION, OMERGA AND OTHER
VERSUS
SOPAN NAGA NARWADE AND ANOTHER .........................
Mr. S.G. Karlekar, Advocate, for applicants.
Mr. L.C. Patil, Advocate, for the non-applicants - original claimants.
..........................
CORAM : A.M. BADAR, J.
DATE : 23RD DECEMBER 2015 PER COURT :
1.
Heard the learned Counsel appearing for applicants as well as the learned Counsel appearing for the non-applicants / original claimants. 2.
These are applications for condonation of delay of 589 days caused in filing appeals under Section 54 of the Land Acquisition Act, 1894, by the acquiring authority. Averments made in the applications are not controverted by filing counter. Delay in filing appeals is sufficiently explained.
(2) C. A. No. 9644 of 2015 & Group 3.
Hence for the stated reasons, Applications are allowed. Delay is condoned. Applications stand disposed of accordingly. ( A.M. BADAR ) JUDGE ................................