Executive Engineer, Medium Project Division, Latur v. The State Of Maharashtra And ANR
{1} 61 sr.no..odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO.7021 OF 2020 IN FA/2466/2019 EXECUTIVE ENGINEER, MEDIUM PROJECT DIVISION, LATUR
VERSUS
THE STATE OF MAHARASHTRA AND ANR ...
Advocate for Applicant : Mr. Vinesh C. Solshe AGP for Respondents - State : Mr. P. M. Kulkarni ...
WITH CA/7022/2020 IN FA/2467/2019 WITH CA/7023/2020 IN FA/2468/2019 WITH CA/7024/2020 IN FA/2469/2019 WITH CA/7025/2020 IN FAST/26407/2018 ...
CORAM : V.K. JADHAV, J.
DATE : 6TH NOVEMBER, 2020.
PER COURT:
Heard learned counsel for the applicant - Acquiring Body. It appears that conditional stay was granted. However, the amount of compensation could not be deposited within the stipulated time. 2.
The learned counsel for the applicant - Acquiring Body seeks extension of time. He submits that the cheque of the compensation amount has been received and the same would be deposited within a period of two weeks.
{2} 61 sr.no..odt 3.
In view of the same, the time to deposit the compensation amount is extended for a period of two weeks. Ofce to accept the cheque if it is deposited within a period of two weeks. 4.
Interim order of stay granted earlier to continue subject to deposit of compensation amount within extended period. 5.
Civil applications are accordingly disposed of. [ V. K. JADHAV ] JUDGE grt/-