← Library
Bombay High CourtWP/7561/2024disposed off

Marathwada Navnirman Lokayat Through Its Secretary v. The State Of Maharashtra Through Its Secretary And Others

2024-07-29Hon'Ble Shri Justice Ravindra V. Ghuge,Hon'Ble Shri Justice Y. G. Khobragade2 pages

2024:BHC-AUG:16599-DB 19wp7561-24

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 19 WRIT PETITION NO. 7561 OF 2024 MARATHWADA NAVNIRMAN LOKAYAT THROUGH ITS SECRETARY

VERSUS

THE STATE OF MAHARASHTRA THROUGH ITS SECRETARY AND OTHERS ...

Mrs. Vashali P. Dama a/w Mr. P. P. Dama, Advocates for the Petitioner Mr. V. M. Kagne, AGP for Respondents State Mr. S. S. Tope, Advocate for Respondent-University

CORAM

: RAVINDRA V. GHUGE & Y. G. KHOBRAGADE, JJ.

DATE : 29th July, 2024 ORDER:

1.

We have briefly heard the learned Advocates for the respective sides.

2.

The learned Advocate for the University submits that as on date, the perspective plan does not include the Petitioner's location for the unaided B.S.W. course. A competent committee has been constituted and which is making a survey of various areas. The Petitioner's representation dated 15.11.2019, pending with Respondent No.5, can be considered. The Petitioner would be given an audience and after considering the representation of the Petitioner, the competent committee would take a decision. Such decision would be communicated to the Petitioner.

19wp7561-24 3.

The learned Advocate for the Petitioner submits on instructions that the Petitioner is agreeable. 4.

In view of the above, this Writ Petition is disposed off. 5.

Let the exercise of taking survey be completed within 90 days. In the event, there is a declaration of the Model Code of Conduct, the same would not be an impediment for completing the above exercise. ( Y. G. KHOBRAGADE, J. ) ( RAVINDRA V. GHUGE, J. ) JPChavan