← Library
Bombay High CourtCA/7956/2025admittedallowedgrantedrule absolute

Branch Manager, Reliance General Insurance Company v. Shobha Arun Gaikwad And ORS

2025-11-06Hon'Ble Shri Justice Sanjay A. Deshmukh2 pages

2025:BHC-AUG:30435 ca7956.25 -1-

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 933 CIVIL APPLICATION NO. 7956 OF 2025 WITH CIVIL APPLICATION NO. 7957 OF 2025 IN FAST/19908/2025 Branch Manager, Reliance General Insurance Company

VERSUS

Shobha Arun Gaikwad And Ors ...

Advocate for Applicant : Mr. Usmanpurkar Aniruddha S Advocate for Respondent Nos. 1 and 2 : Mr. V.S. Badakh .....

CORAM : SANJAY A. DESHMUKH, J.

DATED : 6th NOVEMBER 2025 PER COURT :- 1.

Civil application No. 7956 of 2025 is filed for condonation of delay of 38 days caused in filing the first appeal. 2.

Perused the application and heard learned advocates for the respective parties. Learned advocate for the respondents strongly opposed the application. Considering the reasons stated in the application and the period of delay is only of 38 days, it is clear that the delay is not deliberately caused. Therefore, in the interest of justice, the application is allowed and the delay is condoned. 3.

In first appeal, issue notice to the respondents, returnable on 18.12.2025. Mr. Badakh, learned advocate, waives notice for

ca7956.25 -2respondent Nos.1 and 2 4.

In so far as the civil application No. 7957 of 2025 is concerned, the same is filed for grant of stay to the impugned judgment and award. Perused the application, Heard learned advocates for both sides. For the reasons stated in the application and the fact that entire amount under award is deposited in this Court as per the directions of this Court dated 31.7.2025, the application deserves to be allowed. It is accordingly allowed in terms of prayer clauses "B" and "C" and disposed of.

(SANJAY A. DESHMUKH, J.) rlj/