Dagdoba Bhimrao Sathe v. The State Of Maharashtra And ORS
ca6267.19 IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD CIVIL APPLICATION NO.6267 OF 2019 IN FAST/21186/2018 DAGDOBA BHIMRAO SATHE
VERSUS
THE STATE OF MAHARASHTRA AND OTHERS ...
Mr.L.R. Thakur Advocate h/f. Mr. D.M. Kakade Advocate for Applicant.
Ms.D.S. Jape, A.G.P. for Resp. Nos. 1 and 2.
Mr.Ruturaj C. Patil Advocate for Resp. No. 3. ...
CORAM: ANIL S. KILOR, J.
DATE : 15th MARCH, 2021 ORDER :
1.
This is an application for condonation of delay. There is delay of 777 days for filing an appeal for enhancement of compensation awarded by the Reference Court.
2.
Learned AGP for respondents No. 1 and 2, and learned counsel for respondent No. 3 opposed the application. 3.
For the reasons stated in the application, the civil application is allowed. The delay is condoned. However, it is
ca6267.19 made clear that as regards to entitlement of the applicant - claimant for the interest on the amount of compensation for the delayed period, will be considered at the time of final hearing. 4.
The office is directed to list the first appeal for admission. [ANIL S. KILOR, J.] asb/MAR21