Milind Pralhadrao Phulgirkar v. Allahabad Bank Now Indian Bank Through Its General Manager Hrmd And Another
2025:BHC-AUG:13335-DB 38-CA-7785-2025.odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD 38 CIVIL APPLICATION NO. 7785 OF 2024 IN WPST/12656/2021 MILIND PRALHADRAO PHULGIRKAR
VERSUS
ALLAHABAD BANK NOW INDIAN BANK THROUGH ITS GENERAL MANAGER HRMD AND ANOTHER ....
Mr. Kunal Kale h/f Mr. D. R. Deshmukh, Advocate for the Applicant Mr. P. K. Nikam, Advocate for Respondent Nos. 1 and 2 ....
CORAM : MANGESH S. PATIL & Y. G. KHOBRAGADE, JJ.
DATE : 05.05.2025 PER COURT :- .
By the order of the Registrar (Judicial) dated 10.01.2022, a group of matters was dismissed for non removal of the office objections within three weeks. By way of the present application, the original petitioner is seeking its restoration by condoning the delay of 866 days.
2.
We have heard the other side.
(( 2 )) 38-CA-7785-2025 3.
Though we do not fully agree with the applicant/petitioner regarding the calculation of the delay, considering the nature of the dispute which pertains to the petitioner's employment with the respondent and the grounds mentioned, the civil application is allowed. The delay is condoned, and the writ petition is restored, subject to the petitioner depositing a cost of Rs. 3,000/- with this Court and removing the office objections, both within four weeks from today.
[ Y. G. KHOBRAGADE, J. ] [ MANGESH S. PATIL, J.] SMS