Rajendra Bhikanrao Nimbalkar And Others v. The State Of Maharashtra Through Secretary And Others
2024:BHC-AUG:17541-DB 15wp8103-24
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 15 WRIT PETITION NO. 8103 OF 2024 RAJENDRA BHIKANRAO NIMBALKAR AND OTHERS
VERSUS
THE STATE OF MAHARASHTRA THROUGH SECRETARY AND OTHERS ...
Mr. N. J. Pahune Patil, Advocate for the Petitioners Mr. A. B. Girase, Government Pleader for Respondents State Mr. N. S. Tekale, Advocate for Respondent Nos. 4 to 6
CORAM
: RAVINDRA V. GHUGE & Y. G. KHOBRAGADE, JJ.
DATE : 6th August, 2024 ORDER:
1.
Heard the learned Advocates for the respective sides. 2.
The learned Advocate representing Respondent Nos. 4 to 6, tenders photostat copies of two communications dated 04.07.2024 and 29.07.2024. Both are collectively marked as 'X' for identification. He submits, on instructions from Mr. Pawan F. Chavan, Assistant Engineer, Nandur Madhmeshwar Irrigation Division, Vaijapur, Chh. Sambhajinagar, present in the Court, that the entire proceedings would be completed within 60 days from today and a sale deed would be registered and the payment would be made to the Petitioner.
15wp8103-24 3.
We direct that, since the Respondents have made this statement, the said procedure shall be completed with payment to the Petitioners, within 60 days from today.
4.
The Writ Petition is disposed off ( Y. G. KHOBRAGADE, J. ) ( RAVINDRA V. GHUGE, J. ) JPChavan