The Executive Engineer, Lower Dudhana Project v. Dondiba Eknathrao Pitale And ORS
1 905-CA-13947-10-S
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 13947 OF 2010 IN FAST/23481/2010 THE EXECUTIVE ENGINEER, LOWER DUDHANA PROJECT
VERSUS
DONDIBA EKNATHRAO PITALE AND ORS ...
Advocate for Applicant : Mr. Atul R. Kale.
AGP for Respondents No.2,3 : Mr. A. M. Phule. ...
CORAM : K.K. SONAWANE, J.
DATED : 22nd JUNE, 2018.
Order :- 1.
Heard learned counsel for applicant - Acquiring Body. 2.
Perused the application and other relevant documents. 3.
There shall be stay to the execution and operation of the impugned Judgment and Award dated 05-02-2009 passed by the learned District Judge-3, Jalna, in Land Acquisition Reference No. 38 of 2003, on condition that the applicant-appellant shall deposit the entire amount of compensation pursuant to award along with accrued interest thereon in this court within a period of six weeks from today. Failure to which, the stay granted shall stand vacated automatically without further reference to the Court with liberty to the respondent-original claimant to avail the recourse of law for execution of the award within ambit of law.
4.
Accordingly, civil application stands disposed of. [ K. K. SONAWANE ] JUDGE rrd.