Ashabai Abhimanyu Patil v. The State Of Maharashtra Through Its Secretary And Another

2024-04-03Hon'Ble Shri Justice Ravindra V. Ghuge,Hon'Ble Shri Justice R. M. Joshi3 pages

2024:BHC-AUG:7498-DB - 1 -

IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD WRIT PETITION NO. 8845 OF 2023 Ashabai Abhimanyu Patil age 67 years, occ. Household r/o Pimprala, Tq. & Dist. Jalgaon .. Petitioner versus 1.

State of Maharashtra Through its Secretary Rural Development Department Mantralaya, Mumbai 2.

The Commissioner of Municipal Corporation Jalgaon, Dist. Jalgaon .. Respondents AND WRIT PETITION NO. 12799 OF 2023 Vasant Govind Khadke age 87 years, occ. Nil.

r/o 202, Bhavani Peth, Jalgaon Tq. & Dist. Jalagaon.

.. Petitioner versus 1.

State of Maharashtra Through its Secretary Rural Development Department Mantralaya, Mumbai 2.

The Director of Town Planning Maharashtra State, Pune.

3.

The Assistant Director of Town Planning Jalgaon, Dist. Jalgaon 4.

The Commissioner of Municipal Corporation

- 2 - Jalgaon, Dist. Jalgaon .. Respondents Mr. G. V. Wani, Advocate for the Applicants.

Mr. V. M. Kagne, Mr. P. K. Lakhotiya, AGPs for the State. Mr. M. V. Navandar, Advocate for Municipal Corporation, Jalgaon. CORAM : RAVINDRA V. GHUGE AND R. M. JOSHI, JJ.

DATE : 3rd APRIL, 2024.

ORAL JUDGMENT : ( Per Ravindra V. Ghuge, J.) 1.

Rule. Rule made returnable and heard finally by the consent of the parties.

2.

We have heard the submissions of the learned Advocates for the respective sides and have perused the Petition paper book and affidavit-in-rely filed by the Corporation. The facts of the case are undisputed. On 1st April, 2022, a reservation for composed Depot in Sanction Development Plan (DPR-195) was announced. The development plan came into existence on the said date. Since no development took place and there was no actual acquisition, the Petitioners issued a purchase notice on 7th September, 2018. The learned Advocate for the Corporation submits that in Writ Petition No. 8845/2023, there was no response by the Corporation. In Writ Petition No. 12799/2023, the Corporation tendered it's reply and offered the TDR. The Petitioner refused to accept the TDR.

- 3 - 3.

The law on taking steps within 1 year (as the provision earlier stood) and 2 years (as the provision stands amended), is settled in the case of Girnar Traders vs. State of Maharashtra and others, (2007) 7 SCC 555. The law on offering of TDR and refusal to accept, is also settled in the case of Shree Vinayak Builders and Developers, Nagpur vs. State of Maharashtra and others, 2022(4) Mh.L.J. 739. Offering of TDR is not a step towards acquisition, in view of the judgment in the case of Shree Vinayak Builders (supra). 4.

In view of the above, both these Writ Petitions are allowed. The Corporation is directed to issue a communication to Respondent No. 1 intimating that the lands are released from reservation, within 30 days from today. Respondent No. 1 would thereafter issue appropriate notification in both these cases declaring that reservation is lapsed, under Section127(2) Maharashtra Regional Town Planning Act, within 90 days.

5.

Rule is made absolute in the above terms.

( R. M. JOSHI) ( RAVINDRA V. GHUGE) JUDGE JUDGE dyb