IN THE NATIONAL LOK ADALAT PRESIDED OVER BY

HON'BLE SHRI JUSTICE ANIL S. KILOR, HELD ON 14TH SEPTEMBER, 2019, AT HIGH COURT LEGAL SERVICES SUB-COMMITTEE AT AURANGABAD (Sr. No.153 to 156) 153 FIRST APPEAL (STAMP) NO.21566 OF 2019 WITH CAST/21567/2019 IN FAST/21566/2019 WITH CAST/21568/2019 IN FAST/21566/2019 EX. ENGINEER, LATUR MEDIUM PROJECT LATUR UNDER G.M.I.D.C., AURANGABAD AND ANR

VERSUS

MANIK VISHWANATH DONGRE AND 154 FIRST APPEAL (STAMP) NO.21710 OF 2019 WITH CAST/21711/2019 IN FAST/21710/2019 WITH CAST/21712/2019 IN FAST/21710/2019 EX. ENGINEER, LATUR MEDIUM PROJECT LATUR UNDER G.M.I.D.C., AURANGABAD AND ANR

VERSUS

KESHAV GOPALRAO BHANDARKOTE AND 155 FIRST APPEAL (STAMP) NO.21713 OF 2019 WITH CAST/21714/2019 IN FAST/21713/2019 WITH CAST/21715/2019 IN FAST/21713/2019 EX. ENGINEER, LATUR MEDIUM PROJECT LATUR UNDER G.M.I.D.C., AURANGABAD AND ANR

VERSUS

MAHADEO GOPALRAO BHANDARKOTE AND 156 FIRST APPEAL (STAMP) NO.21722 OF 2019 WITH CAST/21723/2019 IN FAST/21722/2019 WITH CAST/21724/2019 IN FAST/21722/2019 EX. ENGINEER, LATUR MEDIUM PROJECT LATUR UNDER G.M.I.D.C., AURANGABAD AND ANR

2 sr. no.153 to 156.odt

VERSUS

KASHINATH BALWANTRAO HONMALE ...

Advocate for Appellants : Mr. B. R. Surwase AGP for State : Mr. A. M. Phule and Mr. S. P. Sonpawale ...

O R D E R

1.

These are the first appeals (stamp) filed by Acquiring Body namely, Executive Engineer, Medium Project Latur. The Acquiring Body is represented today by learned Advocate Mr. B. R. Survase along Shri Vishnupant Jewalikar, Executive Engineer, Lower Terna Canal Division No.2, Latur and Mr. A. M. Phule and Mr. S. S. Dande, learned AGP for the respondent -State. 2.

The Acquiring Body after verification and necessary calculations has made statement that the decreetal amount granted by reference Court is well within the parameters fixed under the Government Resolution dated 3rd November, 2016 and Corrigendum issued in respect of the said Government Resolution, and therefore, the acquiring body is ready to accept the award passed by the Reference Court in the References filed by the respondent/claimants under Section 18 of the Act, 1894.

3.

The officer present on behalf of the Acquiring Body undertakes

3 sr. no.153 to 156.odt to make the payment within a period of six months from the date of order. The claimants are at liberty to withdraw the same. The undertaking is accepted. The first appeals (stamp) are disposed of. No order as to costs.

4.

The court fee if any paid in the first appeal (stamp), shall be refunded back according to rules. If there is any civil application/applications pending, the same stands disposed of. No order as to costs.

Sd./- Sd./- Sd./- (K. C. Sant) (A.T.A.K. Shaikh) (Anil S. Kilor, J.) Advocate D.J.(Retd.) Head of the Panel Member Member Date: 14.09.2019 Place: Aurangabad mta/